Electricity interconnexion Baixas (Eastern Pyrénées) – Santa LLogia (Catalonia)
Countries: Spain, FranceBorder(s): France-Spain-Andorra,
Territories:
Catalan Cross-border Area, Pyrenees-Mediterranean Euroregion,
Topic(s):
- Spatial planning and development
- Energy
Lead partner: Inelfe (Interconnexion Electrique France-Espagne) : RTE – Réseau de Transport d’Électricité (France) ; REE – Red Eléctrica de España
The French and Spanish electric interconnection was inaugurated in February 2015 in Montesquieu-des-Albères in Eastern Pyrénées. The interconnection is 64km long and brings 320,000 volts. The high-voltage line ensures the electric supply between the two countries. It also promotes renewable energy.
The high-voltage line connects both municipalities of Santa Llogia (Catalonia) and Baixas (Eastern Pyrénées) and is entirely underground. It doubles the electric interconnection level between France and Spain from 1,400MW to 2,800MW. The underground connection is a unique project in the world because it is the first electric connection using the new technology of conversion station (transforming alternating current into direct current). The project promotes sustainable energy with 181 environmental promises and 1 million tons of CO2 saved using renewable energies.
The project was built in three years with 700 millions € invested. The Iberian Peninsula is now connected with the whole European electric system.
Partners
- EIFFAGE
- SAG THEPAULT
- Prysmian Group
- Siemens
Project goals
- Providing the more competitive electricity
- Securing a greater electric supply
- Promoting renewable energies for the energy transition
Project activities
2008: project start
October 1st, 2008: creation of the Inelfe Company by RTE and REE
2012: building start
2015: electric interconnection opening
Project duration
2008-2015
Total cost
700 millions €
EU funding
225 millions €